8. The Following represents a project that should be scheduled using CPM
a. draw the network
b. what is the critical path?
c. what is the expected project completion time?
d. what is the probability of completing this project within 16 days?
| | Times (DAYS) |
Activity | Immediate Predecessors | a | m | b |
A | - | 1 | 3 | 5 |
B | - | 1 | 2 | 3 |
C | A | 1 | 2 | 3 |
D | A | 2 | 3 | 4 |
E | B | 3 | 4 | 11 |
F | C, D | 3 | 4 | 5 |
G | D, E | 1 | 4 | 6 |
H | F, G | 2 | 4 | 5 |