Information on required start-up checks and inspection guidelines for specific mobile cranes is found in _____.
a. ANSI Standard A29.5
b. OSHA 1926, Subpart N, 1926.550
c. ANSI Standard B30.5
d. the manufacturers' manuals
d. the manufacturers' manuals
You might also like to view...
The _____ cut is made when there is a pipe or wire in the wall that the block cannot be slipped over by using the hollow cell.
A. cell punch B. one cell out C. two cells out D. three cells out
What opens and closes the valves in a reciprocating compressor?
A) A cam shaft B) Pressure difference across the valves C) Hydraulic valve lifters D) The piston pushes them open
The symbol for the period of a wave form is:
A) P. B) W. C) T. D) F.
Incorporated into the receiver tank will be a:
A. Service valve B. Bypass check valve C. Sight glass D. All of the above will be part of the receiver tank assembly