What must a contractor show in order to invoke the defense of commercial impracticability?

What will be an ideal response?


To invoke the defense of commercial impracticability, a contractor must
show that something unexpected occurred, the risk of this unexpected
occurrence was not allocated to the contractor, and the occurrence of the
event rendered performance commercially impracticable.

Trades & Technology

You might also like to view...

One method of dynamic braking is to change the function of the motor to that of a(n) ____________________.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

From 1997 to 2002, the forested area in the United States increased to about 0.3 percent from 747million acres to ____ million acres according to the U.S. Forest Service

A) 122 B) 733 C) 655 D) 749

Trades & Technology

Convert 55.0 miles per hour to kilometers per hour

What will be an ideal response?

Trades & Technology

For the electromagnet of Figure P18.1:

a. Find the flux density in the core.
b. Sketch the magnetic flux lines and indicate their direction. c. Indicate the north and south poles of the magnet.

Trades & Technology