What are the three elements a contractor must prove in order to establish an early completion claim?
What will be an ideal response?
To establish an early completion claim, a contractor must prove three
elements: (1) from the outset of the contract, the contractor intended to
complete early, (2) the contractor had the capacity to complete early, and
(3) the contractor would have completed early but for the delay caused by
the owner
You might also like to view...
What effect will an incorrect rear wheel thrust angle have on the front suspension?
A. It will affect steering wheel position B. Steering shimmy C. Cause camber tire wear D. Affect front steering axis inclination
Find the total ?bill for $572.50 for parts, 6 hours of labor at $43.00 per hour, and a 7% sales tax.
Fill in the blank(s) with the appropriate word(s).
When the employer is aware of the hazard and makes no reasonable effort to correct it, OSHA considers this a(n) _____.
a. serious violation b. willful violation c. repeat violation d. egregious violation
According to NEC Section 210.52, laundry areas require at least _____.
a. one receptacle b. two receptacles c. three receptacles d. four receptacles