In the study conducted by Pete Marwick of KPMG, what was the determined percentage of failed projects that exceeded their initial schedule estimates by 30 percent or more?

A. 25%
B. 63%
C. 87%
D. 94%


Answer: C

Computer Science & Information Technology

You might also like to view...

Answer the following questions true (T) or false (F)

1. A derived class destructor always invokes the base class destructor. 2. The base class destructor must be virtual.

Computer Science & Information Technology

When installing RAM, which of the following statements about the first slot to be filled is TRUE?

A) It can be any empty slot. B) It is the slot nearest to the CPU. C) It is the largest slot. D) It is the slot with the lowest number or letter.

Computer Science & Information Technology

Which of the following is one of the steps to apply access lists on a router?

a. Isolate the servers. b. Identify the problem. c. Decide where to place the access list. d. Both a and b. e. Both b and c.

Computer Science & Information Technology

The content of ROM is maintained even when the router is rebooted.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology