Which of the following is NOT a limitation of PERT?
A) Project activities have to be clearly defined, independent, and stable in their relationships.
B) Precedence relationships must be specified and networked together.
C) Only one time estimate can be used for each activity.
D) Time estimates tend to be subjective and are subject to fudging by managers.
E) There is the inherent danger of placing too much emphasis on the critical path.
C
You might also like to view...
Intel's focus on designing complex, expensive microprocessors for PCs enabled competitors to develop cheaper chip sets for non-PC electronics devices. In the strategic intent model of competitive advantage, this is an example of:
A) building layers of advantage. B) loose bricks. C) changing the rules of engagement. D) collaborating. E) none of the above
The development of international accounting standards is the primary function of the
a. IRS. b. AICPA. c. IASB. d. PCOAB.
Under a closed shop agreement, an employer agrees to hire only employees who are already members of a union
Indicate whether the statement is true or false
A franchise in which the franchisee sells products it manufactures from a formula or from ingredients provided by the franchisor is called chain-style business
Indicate whether the statement is true or false