Describe two different network schedules that might be generated for the same project. Explain why

What will be an ideal response?


The schedules that might be developed on a project will generally differ in
the level of detail that is represented. The master schedule might/show activities in a
more generic sense as these would be utilized by upper managers in a firm to quickly
grasp the general status of a project as it pertains to the schedule. For Communication
purposes, the network schedule might be converted to a bar chart. Another network
schedule might be utilized to schedule the tasks of specific crews. This might be
appropriately shown with a network diagram. While the level of detail may not
necessarily show every task that must be performed on a given day, there must be
sufficient detail to permit field personnel to begin to understand the general
scheduling objectives at a particular point in time on a project.

Trades & Technology

You might also like to view...

Windshield washer pumps can be damaged if __________

A) Ethylene glycol antifreeze is used B) Pure water is used in freezing weather C) Contaminated windshield washer fluid is used D) All of the above

Trades & Technology

Explain contributory negligence and how it could be used as a defense by a defendant in a negligence lawsuit?

What will be an ideal response?

Trades & Technology

Generally, to test an electrical loop, the test instrument should be able to supply _____

A) calibration signals B) fieldbus pulses C) pneumatic signals D) power

Trades & Technology

To remove acrylic from a patron's nail, it is best to:

What will be an ideal response?

Trades & Technology