One of the requirements of most contract documents is that the contractor visits the site. Why is the site investigation important?
What will be an ideal response?
First, the contract documents almost always require all bidders to visit the site. Often, in the bid proposal there is a statement that states that the bidder has visited the site. Some of the reasons are to check the following:
1. Site access
2. Availability of utilities (electric, water, telephone)
3. Site drainage
4. Transportation facilities
5. Any required protection or underpinning of adjacent property
6. A rough layout of the site locating proposed storage trailer and equipment locations
7. Subsurface soil conditions (bring a post-hole digger to check this)
You might also like to view...
The power density of a cutting laser can be equal to ____ watts per square inch.
A. 25 B. 100,000 C. 1 million D. 65 million
Why is it important to have objectives for a project proposal predetermined?
What will be an ideal response?
When sketching, it is never necessary to have an eraser available.
Answer the following statement true (T) or false (F)
The more throughput , the ____ the data rate is sent.
A. better B. worse