In a PERT network, the latest (activity) start time is the

A) earliest time that an activity can be finished without delaying the entire project.
B) latest time that an activity can be started without delaying the entire project.
C) earliest time that an activity can start without violation of precedence requirements.
D) latest time that an activity can be finished without delaying the entire project.
E) None of the above


B

Business

You might also like to view...

In a BPMN collaboration model of the purchase process, which of the following best describes the purpose of swimlanes?

A. Clarifying the interaction between pools. B. Showing different jobs in the purchase process. C. Capturing the process complexity. D. Showing the sequence of activities in a pool.

Business

Store location and operations, product and/or service offerings, store image and promotion, and pricing are all controllable variables to a retailer

Indicate whether the statement is true or false

Business

The Boot Department at the Omaha Department Store is being considered for closure. The following information relates to boot activity:    Sales revenue$350,000 Variable costs:   Cost of goods sold 280,000 Sales commissions 30,000 Fixed operating costs 90,000 If 70% of the fixed operating costs are avoidable, should the Boot Department be closed?

A. No, Omaha would be worse off by $13,000. B. Yes, Omaha would be better off by $50,000. C. Yes, Omaha would be better off by $23,000. D. No, Omaha would be worse off by $40,000. E. None of the answers is correct.

Business

A corporation is a legal entity and a partnership is an association

Indicate whether the statement is true or false.

Business