If the sum of all task times is 50 and the cycle time is 10, then ______.
a. the number of workstations is 5
b. the number of workstations is 500
c. the balance efficiency is .88
d. the idle time is 3
a. the number of workstations is 5
You might also like to view...
According to most research, how do employees (especially younger and less experienced employees) generally view their ability to do their job?
A. Extremely underestimate B. Slightly underestimate C. Underestimate in physical jobs and overestimate in mental jobs D. Accurately estimate E. Overestimate
An example of a type I error would be:
A) throwing away a perfectly good banana. B) counting a student's multiple choice response correct when it is actually incorrect. C) releasing a guilty defendant. D) counting a student's multiple choice response correct when it is actually correct.
Fleet Trucking, LLC, buys a white van from Go Motors, Inc , on credit under a guaranty signed by Herbie, Fleet's president, making him personally liable if the company does not pay. Herbie is
a. a surety. b. a lienor. c. a guarantor. d. a creditor.
In the advertising industry, terms such as new advertising, orchestration, and seamless communication were used to describe the concept of
A. diffusion. B. relationship marketing. C. integration. D. positioning. E. channel conflict.