A project consists of seven independent tasks with processing times (in hours) given by 3, 4, 4, 5, 7, 7, and 11.Find the optimal finishing time Opt for N = 3 processors.

A. Opt = 12 hours
B. Opt = 14 hours
C. Opt = 13 hours
D. Opt = 10 hours
E. Opt = 15 hours


Answer: B