What are some grounds for the contractor to terminate the contract under the AIA A201-2007 Document?
What will be an ideal response?
The work must have stopped for a period of 30 consecutive days and the
contractor must have given the owner and architect seven days written
notice of the intent to suspend or terminate. The contractor may also
terminate the contract if there has been a 60-day stoppage that was not their
fault.
You might also like to view...
Nitrogen flows at steady state through a horizontal, insulated pipe with inside diameter of 1.5(in). A pressure drop results from flow through a partially opened valve. Just upstream from the valve the pressure is 100(psia), the temperature is 120(°F), and the average velocity is If the pressure just downstream from the valve is 20(psia), what is the temperature? Assume for air that PV/ T is constant,
= (5/2)R, and
= (7/2)R.
What will be an ideal response?
The most serious Confederate threat to the Union blockade came from
A. British navy vessels on loan to the South. B. swift blockade-running steamers. C. the threat of mutiny from pro-Southern sailors. D. the entrance of the British and French navies as direct military combatants on behalf of the Confederacy. E. the ironclad Merrimack (renamed the Virginia) warship, which destroyed two wooden ships of the Union navy off the Chesapeake Bay and threatened to destroy many more wooden Union warships.
Which of the following are factors of technology innovation?
A. Feasibility B. Manufacturability C. Performance D. Industry Analysis
Was there any shift in American foreign policy between President McKinley and Theodore Roosevelt, the vice president who succeeded him after McKinley's assassination? If so, what was it? In what area, if any, did Roosevelt most clearly depart from McKinley's policies?
What will be an ideal response?