When a small change is to be made in the field which will result in a departure from the original plans and specifications, the owner/ engineer's resident project representative or inspector should do which of the following:

A. Issue a Change Order or Work Directive Change for each such change.
B. Make an oral deal with the contractor, accumulating tradeoffs, so as to avoid paper work and allow the job to look good.
C. Issue Change Orders or Work Directive Changes for major changes only, and issue only a Field Order for the small changes.
D. Allow the contractor to unofficially make the change, as long as the quality of the work is acceptable.


A

Trades & Technology

You might also like to view...

Cattle ranchers had little understanding about how their activities would impact the ecosystem

Indicate whether the statement is true or false

Trades & Technology

The set of values that helps its members understand what the organization considers

important is known as

a. environmental uncertainty b. organizational structure c. organizational design d. corporate culture e. None of these.

Trades & Technology

Technician A says that Honda's hybrid ICE is cranked at 1000 RPM during starting. Technician B says that the operation of the gasoline engine in the Honda hybrid is known as Integrated Motor Assist. Which technician is correct?

A) Technician A only B) Technician B only C) Both technicians D) Neither technician

Trades & Technology

The OBD-II system checks the EGR valve for operation by _______

A) Opening and closing the EGR valve B) Flashing the MIL C) Cycling the DTC system D) Drawing a vacuum on the EGR valve

Trades & Technology