The heir to the throne was due 56 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery

The seven activities, their normal and expedited times (in days) and costs appear in the table. What is the minimum cost to ensure that this project is completed in 56 days? Which activities should be reduced and by how many days?

Activity Normal time Crash time Normal Cost Crash Cost Predecessor
A 5 3 500 1100
B 18 15 900 2300 A
C 12 9 2500 3000 A
D 9 7 500 650 B
E 15 12 3000 5000 B
F 12 10 4000 5000 C, D
G 20 15 3600 4800 E, F


The project before any expediting takes 64 days. The activities that should be expedited are D, for 2 days at $75/day; G for 5 days at $240/days; and A for 1 day at $300/day. The total cost to expedite is $1,650 in addition to the normal cost of $15,000.

Business

You might also like to view...

During which stage of the reactionary process is the most useful time to interview individuals who are dealing with fraud?

a. acceptance b. bargaining c. depression d. anger

Business

Which of the following is true regarding JIT systems?

A. JIT requires suppliers to respond to very short order lead times and the customer's production schedule. B. JIT usually entails less frequent deliveries. C. JIT requires manufacturers to add new warehouses. D. Manufacturers must locate their facilities next to important customers in order to practice JIT. E. JIT systems do not have backup inventory.

Business

Which of the following methods of communication is typically used to create goodwill within an organization?

A. award ceremonies B. grievance committees C. corporate picnics D. annual reports E. organizational newsletters

Business

Monopoly power was often granted by early corporate charters

a. True b. False Indicate whether the statement is true or false

Business