The project team or contractor must avoid ____, which is informally making changes to the project scope without appropriate approval
a. scope change
b. scope creep
c. editing the project scope document
d. updating the work breakdown structure
b
You might also like to view...
In 2002, the United States Congress created the Consumer Financial Protection Bureau (CFPB) as part of the Sarbanes-Oxley Act.
Answer the following statement true (T) or false (F)
Which of the following is an exception that would force going-rate prices to deviate from unit
costs? A) sudden spikes in prices due to perceived future cost increases B) shifts in the perception of product category, such as a product previously considered a luxury item becoming a commodity C) presence of a few major players in the industry D) long periods of stable economic conditions that bring about economic prosperity
Peterson Inc has the following information available regarding one of the projects it is considering: Initial investment $75,000 PV of cash inflows $100,000 Internal rate of return 15% The profitability index of this project is:
A) 1.33. B) 0.75. C) 0.15. D) 0.33.
Agent wholesalers-particularly manufacturers' agents and brokers-are often order getters.
Answer the following statement true (T) or false (F)