The forward pass through a project network determines the critical path.

Answer the following statement true (T) or false (F)


False

The forward pass starts with the first project activity(ies) and traces each path (chain of sequential activities) through the network to the last project activity(ies). The forward pass assumes every activity will start the instant in time when the last of its predecessors is finished. It determines the early start and early finish for activities and the project duration. The backward pass determines the critical path.

Business

You might also like to view...

To share information such as hashtags and WiFi log-in information, include

A) a title slide. B) navigation slides. C) handouts. D) agenda and program detail slides. E) hyperlinks.

Business

The times interest earned ratio is a measure of

a. profitability; b. liquidity; c. leverage; d. interest return; e. return on revenue

Business

The purpose of adding a graph in a report is to _____

A) allow the reader to identify trends B) determine exact values C) arrange data in columns and rows D) to see relationships be reading down or across E) to replace the written word

Business

Which of the following statements is true about negotiation terms?

Business