Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity
A) 6
B) 7
C) 9
D) 5
E) None of the above
A
You might also like to view...
Martha draws a check payable to the order of Stella. Stella indorses the check to Karen. But Leslie steals the check from Karen, forges Karen's indorsement, and cashes the check at a liquor store
When the forgery is exposed, whom can the liquor store legally recover from? A) Martha B) Leslie C) Karen D) Stella
It is important to display empathy when dealing with complaining customers
Indicate whether the statement is true or false
Because of differences in the expected returns on different investments, the standard deviation is not always an adequate measure of risk. However, the coefficient of variation adjusts for differences in expected returns and thus allows investors to make better comparisons of investments' stand-alone risk.
Answer the following statement true (T) or false (F)
Community Bank receives a check drawn by Dennis. The check lacks a proper indorsement. Payment can be postponed without dishonor
a. indefinitely. b. under no circumstances. c. for thirty days. d. until the proper indorsement is obtained.