For an activity, assume the early start is 3 weeks, early finish is 6 weeks, late start is 4 weeks, and late finish is 7 weeks. What is the activity's slack?

A) 3 weeks
B) 4 weeks
C) 1 week
D) 2 weeks


C

Business

You might also like to view...

Which channel and medium combination takes longer to create and distribute but allows the sender to avoid immediate interactions?

A) Written, printed B) Written, digital C) Oral, printed D) Visual, digital E) Oral, digital

Business

Opportunity costs are profits lost because money is tied up in inventory.

Answer the following statement true (T) or false (F)

Business

What would be the carrying value of X's Investment in Y at the end of 2018?

A) $98,800 B) $97,500 C) $91,200 D) $100,000

Business

Penny, age 52, takes a distribution of $30,000 from her Traditional IRA account. She plans to deposit it in an IRA with a different bank. Shortly after the distribution she drives her car through the front window of her credit union in a freak accident,

and uses the funds to pay for the damages. What income and/or penalties related to the failure to rollover the IRA must she show on her tax return ?

Business