If the most optimistic time for completing an activity is 14, the most likely time is 16, and the most pessimistic time is 30, then the estimated time for the activity is ______.
A. 18
B. 19
C. 20
D. 21
A. 18
You might also like to view...
A(n) ________ is a document of title issued by a common carrier stating that the bailor has title to the bailed goods
A) bill of lading B) accession C) freight forwarder D) delivery order
Webvan designed a supply chain with large warehouses in several major cities in the United States, from which groceries were delivered to customer homes. They failed partly because of
A) low demand for their service. B) slow inventory turnover compared to industry averages. C) higher labor costs for picking orders. D) poor quality products.
Product and target market characteristics usually determine the type of coverage a product receives. For which of the following products is selective distribution most appropriate?
A. Gasoline B. Jaguar automobiles C. Skippy peanut butter D. Laundry detergent E. Organic foods
GATT 1947 applied to:
a. trade in goods. b. trade in services. c. trade in textiles. d. All of the above