The ____ method of construction was originally developed for slabs that were to be poured at ground level and then lifted into place for multilevel structures.

A. pre-tensioning
B. static-tensioning
C. planned-tensioning
D. post-tensioning


Answer: D

Trades & Technology

You might also like to view...

Offset drives, such as V-belts, gears, and chain drives, can be lined up more easily than direct drives.

Answer the following statement true (T) or false (F)

Trades & Technology

An example of a welding fabrication decimal fraction problem would be to find the total length of two pieces of pipe when one is 5.5 ft and the other is 2.25 ft.

Answer the following statement true (T) or false (F)

Trades & Technology

Standing seam is a method used to _____.

a. seal insulation seams b. seal fire-rated assemblies c. apply firestopping material d. join preinsulated panels

Trades & Technology

What caused the carrier pigeon to become extinct?

What will be an ideal response?

Trades & Technology