What type of sequencing relationship is used when two activities should be completed at the same time despite the fact that they might have different durations?

A. Start to Start
B. Finish to Finish
C. Start to Finish
D. Finish to Start


Answer: B

Trades & Technology

You might also like to view...

A family living in a home is exposed to 0.008 mg/L of 1,4-dioxane in their drinking water. Calculate the lifetime risk for

a. Adult male b. Adult female c. Child What will be an ideal response?

Trades & Technology

Which of the following is not a kind of linear perspective drawing?

A two-point B. isometric C. two-point D. kinetic

Trades & Technology

Of the following combination of values, ________, ________, and ________ leads to the highest risk.

A. Low financial investment; high uncertainty; low hazard B. Low financial investment; low uncertainty; low hazard C. High financial investment; high uncertainty; high hazard D. Low financial investment; high uncertainty; high hazard

Trades & Technology

Some states require auto technicians to be ASE certified to perform repairs.

Answer the following statement true (T) or false (F)

Trades & Technology