Your next project consists of 5 consecutive 10-day activities, each estimated by a different worker in your organization

You have all secretly added your own safety margin of 4 days into your estimates and you watch in horror as the project manager whips out his copy of Critical Chain and slams it on the table midway through their first project meeting. "I'm taking your buffers and making them my own," he bellows. You recoil from this news and do some quick mental arithmetic. Now that you know the project manager is a Goldratt disciple, you know that the new project buffer will be:
A) 25 days
B) 20 days
C) 15 days
D) 10 days


D

Business

You might also like to view...

The format and content of supplementary information which is not required by GASB is up to the discretion of the reporting entity.

Answer the following statement true (T) or false (F)

Business

Which one of the following is not one of the arrangements used by organizations to offer employee assistance programs?

A. In-house B. Outsource C. Consortium D. Consultant

Business

Runyon Inc. reported the following results from last year's operations:   Sales$16,800,000Variable expenses 12,230,000Contribution margin 4,570,000Fixed expenses 3,394,000Net operating income$1,176,000?The company's average operating assets were $7,000,000.?Last year's turnover was closest to:

A. 2.40 B. 0.42 C. 14.29 D. 0.07

Business

Gigabit Ethernet adapters can support up to 1 Gbps (billion bits per second) or 1000 Mbps

Indicate whether the statement is true or false

Business