What is the average lateness of these seven jobs if they are scheduled using the critical ratio criterion?

Job Process Time Due Date
Job 1 15 23
Job 2 7 15
Job 3 12 34
Job 4 8 16
Job 5 11 27
Job 6 10 19
Job 7 13 28

A) 24.3
B) 21.7
C) 22.5
D) 23.4


Answer: B

Business

You might also like to view...

The probabilities of different returns on a stock over the year are: Probability Return 10% ?5% 15% 0% 20% 5% 30% 10% 25% 20% The standard deviation of the return on the stock is about ____ percent.

A. 5 B. 8 C. 11 D. 14

Business

Which of the following statements is not correct about the alternative hypothesis?

A) There is no way to determine whether the alternative hypothesis is true. B) The alternative hypothesis represents the conclusion for which evidence is sought. C) The alternative hypothesis is the opposite of the null hypothesis. D) None of the statements are correct.

Business

Discuss the percentage-of-sales method used for setting the total budget for advertising

What will be an ideal response?

Business

The Innovator's Dilemma suggests that established companies can take advantage of ________ without hindering existing relationships with customers, partners, and stakeholders.

A. Sustaining technology B. Collective intelligence C. Existing investments D. Disruptive technology

Business