Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity

A) 3
B) 6
C) 9
D) 18
E) None of the above


C

Business

You might also like to view...

Innovations is a producer of electronic circuits that power a variety of technological devices produced by other companies. Innovations sells its products to ________ markets

A) business B) government C) consumer D) internal E) financial

Business

Ethically appropriate methods of leadership are central to becoming an ethical leader.

Answer the following statement true (T) or false (F)

Business

What is the purpose of using the DICE model?

What will be an ideal response?

Business

Which of the following statements is (are) true concerning the joint and survivor annuity settlement option?

I. Under this option, payments begin after the first annuitant dies. II. This settlement option is often selected by married couples. A) I only B) II only C) both I and II D) neither I nor II

Business