Early finish time (EF) ______.

A. is the earliest possible date in the year on which an activity can be completed
B. is calculated by subtracting the duration for an activity to the ES
C. is the earliest possible time on a day on which an activity can be completed
D. is calculated by subtracting the duration for an activity from the ES


A. is the earliest possible date in the year on which an activity can be completed

Business

You might also like to view...

Answer the following statements true (T) or false (F)

1.Weblogs are often not effective means of emotional purging and insight. 2.Similar attitudes about intimacy and disclosure can be found across cultures. 3.Every relationship should be sustained or maintained at whatever the cost. 4.Roger is an abusive person and would be expected to timidly seek to dominate others. 5.Physical forms of relational abuse are toxic and leave scars from which victims find it difficult to recover, but not psychological scars.

Business

Lengthening a product line beyond its current range is referred to as product line ________

A) filling B) strengthening C) mixing D) stretching E) widening

Business

What is the purpose of marketing research?

What will be an ideal response?

Business

An internal control system consists of the policies and procedures companies use to protect assets, ensure reliable accounting, promote efficient operations, and uphold company policies.

Answer the following statement true (T) or false (F)

Business