Using effort-driven scheduling, calculate the following. If you have 1 employee and the duration is 32 hours, the work would require ________ days

A) 4 B) 32 C) 64 D) 8


A

Computer Science & Information Technology

You might also like to view...

The crosshair icon determines the point of origin automatically only when you enter values directly into the Control panel.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology

?The hardening process that makes a system more secure is fully automatic.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology

The ____________ property can be used with multidimensional arrays to get the total number of elements in all dimensions.

Fill in the blank(s) with the appropriate word(s).

Computer Science & Information Technology

An organization that is setting up a key card entry control system should:

a. Establish different zones and determine which personnel should be able to access each zone b. Establish one zone and assign all personnel to the zone c. Determine, for each employee, whether they should be able to access each controlled door d. Permit employees to access all general-entrance doors and issue metal keys to more sensitive areas

Computer Science & Information Technology