Mick has a project consisting of eight activities as listed in the table (with durations in days). He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below
Determine the early and late start and finish times for all of these activities.
Activity Activity time
A 6
B 8
C 5
D 9
E 12
F 11
G 6
H 3
The table shows the requested information.
Activity Activity time Early Start Early Finish Late Start Late Finish
A 6 0 6 0 6
B 8 0 8 1 9
C 5 6 11 24 29
D 9 8 17 9 18
E 12 6 18 6 18
F 11 18 29 18 29
G 6 29 35 29 35
H 3 35 38 35 38
You might also like to view...
The current replacement cost of an asset is the amount a firm would have to pay to obtain another asset with identical service potential; it is an entry value that reflects economic conditions at the measurement date
Indicate whether the statement is true or false
The Senate must confirm each justice that is nominated to the federal courts
Indicate whether the statement is true or false
Which of the following types of bonds protects a bondholder against increases in interest rates?
A. Floating-rate bonds B. Income bonds C. Bonds with call provisions D. Municipal bonds E. Mortgage bonds
The social mirror is based on our memory of how others have reacted toward us or treated us.
Answer the following statement true (T) or false (F)