Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint?
A. Time
B. People
C. Technical
D. Equipment
E. Physical
Answer: B
You might also like to view...
Explain the difference between a title fly and a title page
What will be an ideal response?
A materiality level where the auditor believes that the errors below that level would not, even when aggregated with all other misstatements, be material to the financial statements is often based on whether something is considered clearly trivial
a. True b. False Indicate whether the statement is true or false
Which of the following clauses ensures that a basic loop runs at least once?
A. EXIT WHEN B. WHERE C. CASE D. LOOP
Hugh Willmott (2002) applied two concepts from George Orwell’s 1984 to highlight the dark side of organizational culture: one is ‘Newspeak’, and the other is _________ which refers to the capacity to hold mutually contradictory views at the same time.
a. Big brother b. Oceania c. Doublethink d. Corporate culture