Fred's Fabrication has the following aggregate demand requirements and other data for the upcoming four quarters

Quarter Demand Previous quarter's output 800 units
1 700 Beginning inventory 0 units
2 900 Stockout cost $100 per unit
3 1200 Inventory holding cost $10 per unit at end of quarter
4 600 Hiring workers $20 per unit
Laying off workers $40 per unit
Subcontracting cost $200 per unit
Unit cost $100 per unit

Which of the following production plans is better: Plan A–chase demand by hiring and layoffs; Plan B–pure level strategy, or Plan C–700 level with the remainder by subcontracting?


Plan A has cost of $378,000, plan B has cost of $368,500, and plan C has cost of $425,000. Plan B has the lowest cost. Note that Plan C has an ending inventory of 100 units, which is the result of level production that exceeds demand in the last quarter.

Plan A — Chase strategy
Fred's Fabrication Solution
Demand Regular Time Capacity Regular Time Production Units Increase Units Decrease
Initial Inventory
Period 1 700. 1,200. 700. 0. 100.
Period 2 900. 1,200. 900. 200. 0.
Period 3 1,200. 1,200. 1,200. 300. 0.
Period 4 600. 1,200. 600. 0. 600.
Total (units) 3,400. 4,800. 3,400. 500. 700.
@$100/unit @$20/unit @$40/unit
Subtotal Costs 340,000. 10,000. 28,000.
Total Cost 378,000.

Plan B — Level production, 850 per quarter
Fred's Fabrication Solution
Demand Regular Time Capacity Regular Time Production Inventory (end PD) Shortage (end PD) Units Increase
Initial Inventory 0.
Period 1 700. 1,200. 850. 150. 0. 50.
Period 2 900. 1,200. 850. 100. 0. 0.
Period 3 1,200. 1,200. 850. 0. 250. 0.
Period 4 600. 1,200. 850. 0. 0. 0.
Total (units) 3,400. 4,800. 3,400. 250. 250. 50.
@$100/unit @$10/unit @$100/unit @$20/unit
Subtotal Costs 340,000. 2,500. 25,000. 1,000.
Total Cost 368,500.

Plan C — 700 units level, with subcontracting

Demand Regular Time Production Subcon-
tracting Production Regular Time Production Subcon-
tracting Inventory (end PD) Units Decrease
Initial Inventory 0.
Period 1 700. 700. 0. 700. 0. 0. 100.
Period 2 900. 700. 200. 700. 200. 0. 0.
Period 3 1,200. 700. 500. 700. 500. 0. 0.
Period 4 600. 700. 0. 700. 0. 100. 0.
Total (units) 3,400. 2,800. 700. 2,800. 700. 100. 100.
@$100/unit @$200/unit @$10/unit @$40/unit
Subtotal Costs 280,000. 140,000. 1,000. 4,000.
Total Cost 425,000.

Business

You might also like to view...

Which of the following best refers to an organizational stress management program that attempts to change the intensity and type of stressors impacting employees and may include job rotation, job enrichment, employee empowerment, goal setting, and regular feedback?

A. Stress reduction intervention program B. Employee assistance program C. Stress management training program D. Health promotion program

Business

Alex has decided to lead his followers by sharing responsibility with the group, which distributes influence among his workgroup. Alex is demonstrating ______.

A. transformational leadership B. shared leadership C. empowering leadership D. self-leadership

Business

Risk is the uncertainty about the return we will earn.

Answer the following statement true (T) or false (F)

Business

Suggestions from everyone but ______ have been received

A) they B) them

Business