Determine the cost to install the rebar for the foundation walls in Figures 11.38 and 10.39 using a productivity of 11.3 labor hours per ton and an average labor rate of $31.26 per labor hour. From Problem 43, the weight of the rebar is 5,778 pounds.


What will be an ideal response?


Labor hour = 10.3 lhr per ton × 5,778 pounds / 2,000 pounds per ton = 29.8 lhr

Labor cost = 29.8 lhr × $31.26/lhr = $931.55