Solve the linear programming problem.An automotive glass plant must be able to fill orders for 230 truck windshields, 350 auto windshields, and 310 RV windshields. Because the first-shift crews are more experienced, they are each able to make 7 truck windshields, 12 auto windshields, and 9 RV windshields. The second-shift crews are able to produce 4 truck windshields, 12 auto windshields, and 7 RV windshields. The first-shift crews cost the company $360.00 per crew per shift, and the second-shift crews cost $310.00 per crew per shift. The company's facilities will handle at most 50 crews on each shift, and they must have at least 10 crews come in to keep the plant running. How many first-shift and how many second-shift crews should be scheduled to minimize costs?
A. 37 first-shift crews and 36 second-shift crews
B. 43 first-shift crews and 24 second-shift crews
C. 28 first-shift crews and 10 second-shift crews
D. 51 first-shift crews and 17 second-shift crews
Answer: C
You might also like to view...
Solve the problem.An upholsterer wants to reupholster 120 chairs for a banquet hall. If each chair needs pound of brass tacks, how many pounds of brass tacks are needed?
A. 20 pounds B. 72 pounds C. 720 pounds D. 2 pounds
Simplify the expression.
?
What will be an ideal response?
Use the Remainder Theorem to find the remainder when f(x) is divided by x - c.f(x) = x4 + 8x3 + 12x2; x + 1
A. R = 5 B. R = 21 C. R = -5 D. R = -21
Answer the question.If the vertex of the graph of a quadratic function lies in quadrant III and the graph is concave down, how many x-intercepts does the graph have?
A. 1 B. 3 C. 0 D. 2