In a typical building project, the GC must provide (and pay for) all three surety bonds?bid bond, performance bond, and payment bond?to the owner. In certain situations, the owner may waive bid bond requirement. Mention one such situation.

What will be an ideal response?


Bid bond may be waived in situations where the owner is familiar with the GC's financial standing and ability to
perform the work, such as in invitational bidding project delivery method.

Trades & Technology

You might also like to view...

Find the estimated emissions listed below for an Uncontrolled (Post-NSPS) Large Wall-fired Boiler natural gas cogeneration facility that burns 500 million standard cubic feet (scf) of natural gas per year. Use the EPA’s AP-42 (Volume 1, 5th ed.) Chapter 1: External Combustion Sources Emission Factors for Natural Gas Combustion.

a. Tons of NOx emitted per year b. Tons of CO emitted per year What will be an ideal response?

Trades & Technology

Al instalar un aparato montado en superficie que pese más de 50 libras,

a. siempre debe soportarse de manera independiente a la caja de distribución. b. puede ser soportado por la caja de distribución si la caja esta especificada para más de 50 libras. c. puede ser soportado por una caja estándar de distribución sin soporte adicional. d. puede afianzarse a una caja estándar de distribución si se sujeta firmemente

Trades & Technology

The vision incorporates the basic tenants of the mission statement.

Answer the following statement true (T) or false (F)

Trades & Technology

Hydraulic valve lifters can make a ticking noise when the engine is running if ________

A) Valve lash is too close B) Valve lash is too loose C) Lobe centerline is over 110° D) Both A and C

Trades & Technology