Consider a work center with a demand rate of 20 parts per hour and using a container that can hold 5 parts. It is estimated that the container takes 30 minutes to cycle through the work cell. Assume a safety stock level of 10 percent. What is the value of C for this system?

a. 5
b. 0.5
c. 0.1
d. 20