Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days

a. day 5
b. day 3
c. day 1
d. Cannot be calculated based upon information given.


b

Business

You might also like to view...

The formula for calculating the variable overhead efficiency variance is

A) (AVORxAH) - (SVORxAH) B) (AVOR - SVOR)SH C) (AH - SH)SVOR D) (AH - SH)AVOR E) none of these

Business

Since Dillards operates in a complex and dynamic environment, its store managers are given significant freedom to run their stores. This indicates that top leaders at Dillards

A. centralize decision making. B. deemphasize lower-level management training. C. control their managers tightly. D. deemphasize lower-level management accountability. E. decentralize authority.

Business

A ________ is an order for a brokerage firm to buy a stock when the price rises to a specified level

A) stop order B) buy stop order C) sell stop order D) go order

Business

Bonds from a single issue that have staggered maturity dates are called serial bonds.

Answer the following statement true (T) or false (F)

Business