Use the earned value table for Project Makeready to calculate the estimated cost to completion
Activity 7 14 21 28 35 42 49 Plan % Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) $4,285
B) $5,250
C) $6,050
D) $7,645
D
You might also like to view...
Trust Service criteria cover:
A. software design. B. confidentiality. C. hardware design. D. physical protection of computer systems.
Which preference category within the Myers-Briggs reflects how individual make decisions?
a. Extraversion or Introversion b. Sensing or Intuition c. Thinking or Feeling d. Judging or Perceiving
The select time is the average observed time based only on representative times
Indicate whether the statement is true or false
Why is the beneficiary decision so important when buying life insurance?
What will be an ideal response?