Solve the problem.A commercial building contractor is trying to decide which of two projects to commit her company to. Project A will yield a profit of $50,000 with a probability of 0.6, a profit of $83,000 with a probability of 0.3, and a profit of $10,000 with a probability of 0.1.Project B will yield a profit of $100,000 with a probability of 0.1, a profit of $66,000 with a probability of 0.7, and a loss of $20,000 with a probability of 0.2.Find the expected profit for each project. Based on expected values, which project should the contractor choose?
A. Project A: $55,900
Project B: $60,200
Contractor should choose project B
B. Project A: $46,900
Project B: $52,200
Contractor should choose project B
C. Project A:$55,900
Project B: $52,200
Contractor should choose project A
D. Project A: $47,666
Project B: $48,666
Contractor should choose project A
Answer: C
You might also like to view...
Find two paths of approach from which one can conclude that the function has no limit as (x, y) approaches (0, 0).f(x, y) =
What will be an ideal response?
Solve the absolute value equation.|1.7x + 2.5| = |x - 2|
A. no solution B. x = -0.852, -3.857 C. x = -1.278, -1.687 D. x = -0.185, -6.429
Solve the problem.Suppose your job is to take phone orders for automotive parts. Use the table below to answer the following questions. Write the correct part number that matches what you hear the customer say on the phone.?"We received all parts except the 1 and 7 hundredths size."
A. H B. F C. C D. G
Provide an appropriate response.(56 + 89) + 103 = 24856 + (89 + 103) = 248This is an example of the .
A. commutative property of addition B. associative property of addition C. associative property of multiplication D. commutative property of multiplication