If any task along a critical path falls behind schedule, the entire project will be delayed.

Answer the following statement true (T) or false (F)


True

Rationale: If any task on the critical path falls behind schedule, the entire project will be delayed.

Computer Science & Information Technology

You might also like to view...

Write an HTML page that contains a text field for a name and a button. When the button is clicked check that the text field has only alphabetic characters (no numbers) in it. If not, use an alert dialog to inform the user.

What will be an ideal response?

Computer Science & Information Technology

?Case 4-2 Arnold takes his networking trainer Ron's help to learn about the array of new communications technologies that are being used today. Ron provides various instances and examples that can help Arnold identify different communication protocols and standards. Ron explains to Arnold how the current standards for cellular networks today work in the United States and many other countries. Based on the explanation, which of the following should Arnold do when the 4G usage on his cell phone exceeds the set limit?

A. ?Not access Internet on his phone B. ?Switch to 3G network instead of 4G C. ?Share his device with another 4G-enabled device D. ?Establish a secure connection with a nearby home network

Computer Science & Information Technology

What happens in a method if there is an exception thrown in a try block but there is no catch block following the try block?

A. The program ignores the exception. B. The program will not compile without a complete try/catch structure. C. The program terminates immediately. D. The program throws an exception and proceeds to execute the finally block.

Computer Science & Information Technology

What is the biggest differentiator among Ethernet hubs?

A. the size of the power supply B. the types of connectors C. the number of ports D. the price

Computer Science & Information Technology