There are 5 jobs (A, B, C, D, E) that need to be completed in a work center. The due dates are the 10th, 13th, 9th, 20th, and 15th respectively with process times of 7, 12, 7, 20, and 10 respectively as well
If today is the 1st of the month calculate the critical ratio for each and use this value to sequence the jobs in the order they should be started.
A = (10 - 1)/7 = 1.29
B = (13 - 1)/12 = 1.00
C = (9 - 1)/7 = 1.14
D = (20 - 1)/20 = 0.95
E = (15 - 1)/10 = 1.40
Thus the sequence would be DBCAE, or lowest critical ratio first
You might also like to view...
On January 1, 2017, Doyle Manufacturing Corporation purchased a machine for $40,000,000
The corporation expects to use the machine for 24,000 hours over the next six years. The estimated residual value of the machine at the end of the sixth year is $40,000. The corporation used the machine for 3,600 hours in 2017 and 5,000 hours in 2018. Calculate depreciation expense for 2018 if the company uses the units-of-production method of depreciation. What will be an ideal response
What acronym describes the technology that utilizes an integrated circuit and a tag antenna to transmit and record information on a product?
A) RFID B) CPFR C) MAPE D) MSE E) QFD
The error term that corresponds to the 3rd quarter in year 6 is:
A) -1.08 B) 9.24 C) -3.56 D) -101.63
What is the call option premium given the following information? Stock price$47 Strike price$40 Standard deviation 44percentRisk-free rate 4percentDividend yield 0percentTime to maturity 3months
A. $8.58 B. $7.16 C. $7.78 D. $9.49 E. $9.03