In line balancing, the number of workstations required (N) is given by ______.
A. cycle time/flow time
B. idle time/cycle time
C. sum of all task times/cycle time
D. sum of all task times/flow time
C. sum of all task times/cycle time
You might also like to view...
Briefly describe acknowledgment as a form of listening.
What will be an ideal response?
______ are publications, either printed or electronic, that are produced on a regular basis, such as newspapers, magazines, and journals.
a. Proceedings b. Periodicals c. Primary sources d. Secondary sources
Which of the following is when the team moves through the storming phase and establishes productive norms?
A. high-performing team B. real team C. pseudoteam D. potential team
Which method of preparing the statement of cash flows starts with the total for net income and removes the effects of gains and losses from nonoperating transactions, and then adds or subtracts balance sheet changes involving operating accounts?
a. direct method b. fixed method c. indirect method d. funds flow method e. variable method