If the most optimistic and pessimistic times for a task are 3 and 15 days, respectively, then the variance for the duration of the activity is ______.

A. 3.00
B. 4.00
C. 5.00
D. 6.00


B. 4.00

Business

You might also like to view...

Which of the following statements is true?

A. The yield curve slopes downward when the term spread is positive. B. Researchers suggest that the smaller the term spread, the higher the chance is of a recession in the coming year. C. The yield curve slopes upward when the term spread is negative D. Researchers suggest that the larger the spread, the higher the chance is of a recession in the coming year.

Business

Marketing managers are interested in variables such as usage rate and degree of loyalty. Which category of descriptor variable do these fall under?

A) geographic B) demographic C) psychographic D) behavioral

Business

The amount of the "adjusted balance" appearing on the bank reconciliation as of a given date is the amount that is shown on the balance sheet for that date

Indicate whether the statement is true or false

Business

Price changes of variable overhead items are easily controlled by production supervisors

Indicate whether the statement is true or false

Business