A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

A) 631
B) 689
C) 807
D) 833
E) 1009


C

Business

You might also like to view...

_____ are difficulties that inhibit the achievement of goals. For example, the lack of parking may be the main reason why a new restaurant is failing.

A. Objectives B. Synergies C. Values D. Problems E. Alternatives

Business

Answer the following statements true (T) or false (F)

1.Despite younger leaders and older leaders growing up in quite different eras, their formative experiences with respect to leadership are remarkably similar. 2.Charismatic leadership in whatever its form constitutes a moral “slippery slope.” 3.Leadership is always provided by those in formal positions of authority. 4.To provide leadership in moving a group in a new direction, a leader does not have to exercise power or control.

Business

The three stages that comprise the change model developed by Kurt Lewin are ______, ______, and ______.

What will be an ideal response?

Business

When you provide credit information about another person, you have an ethical and legal obligation to

a. yourself. b. the credit applicant. c. the business from whom credit is requested. d. all of the above.

Business