Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks. What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)

A) 0.68
B) 0.78
C) 0.22
D) 0.32
E) None of the above


B

Business

You might also like to view...

Good leaders will expect that effective followers ______.

a. might not have learned how to listen effectively b. might listen well, but might not have yet learned how to accept feedback c. will listen to and accept feedback that is coming down from a leader d. might have neither learned to listen well, nor accept feedback yet

Business

Explain how to compute dividend yield and discuss how it is used in analysis of a company's financial condition.

What will be an ideal response?

Business

Real property cannot be turned into personal property by detaching it from the land.

Answer the following statement true (T) or false (F)

Business

Describe how a back-to-back loan is used

What will be an ideal response?

Business