If the most optimistic time for completing an activity is 3, the most likely time is 5, and the most pessimistic time is 12, then the estimated time for the activity is ______.
A. 5.83
B. 6.42
C. 10.58
D. 9.11
A. 5.83
You might also like to view...
For situations in which there is an immediate threat of contamination due to a release of hazardous materials, Superfund does not require immediate removal of the hazardous materials in question.
Answer the following statement true (T) or false (F)
When nations are of similar size and have similar taste patterns, the gains from trade
a. are shared equally between them. b. are impossible to determine. c. are too small, so that trading is not beneficial. d. are determined by the nation that has comparative advantage in the more essential product.
Which of the following statements is true?
a. Autocratic leaders are likely to believe in the development of autonomous teams. b. Leaders should encourage their followers to work in virtual teams whenever possible. c. The overall goal for the formal leader should be to enable successful delegation of decision-making to followers. d. The most successful teams will have an equal number of in-group members and out-group members.
Which of the following is reduced by a just-in-time operations?
A) Inspection time and moving time B) Only storage time C) Moving time and processing time D) Inspection time and processing time