A project consists of six activities (all times are given in days). Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using an early start schedule

Activity Activity time Activity Cost Predecessor
K 10 140
L 8 64 K, M
M 12 96
N 6 120 M
P 14 168 L
Q 12 144 N


Highest resource usage occurs during days 13 through 18 with activities L and N requiring a combined 28 units of resources. The lowest usage of 8 resource units occurs on days 11 and 12 for activity M.

Business

You might also like to view...

Manufacturers that add online channels may avoid alienating retailers or other intermediaries by offering different brands or products through online channels than in stores

Indicate whether the statement is true or false

Business

Treasury shares plus outstanding shares equal

a. unissued shares. b. subscribed shares. c. authorized shares. d. issued shares.

Business

The first step in planning a presentation is to determine _____

A) who is the audience B) how to achieve my desired outcome C) where the presentation will be given D) how the message will be delivered E) the purpose of the presentation

Business

It is easy to identify a person's motives because they are clearly reflected in that person’s behavior.?

Indicate whether the statement is true or false

Business