What are the differences in rules of the courts in the GEM Industrial, Inc. v. Sun Trust Bank and White v. AAMG Construction Lender Center on one hand, and Alpine Bank v. Hubbell on the other?
What will be an ideal response?
In GEM and White, both courts found the construction lender liable to the
owner when the lender’s inspector had discovered defective or incomplete
construction, yet still made the payments to the contractor. In Hubbell, the
court enforced a Limitation of Responsibility provision in the loan
agreement and found the lender not liable to the owner/borrower. The
owner could not rely upon the bank to protect the owner from the
contractor’s improper performance.
You might also like to view...
Para limitar la impedancia, los transformadores de aislamiento deben ser de _____ o menos.
a. 5 kVA b. 10 kVA c. 12 kVA d. 20 kVA
What kind of curing agent do you use when applying gel nails?
What will be an ideal response?
To calculate the CFM required to provide a given number of air changes in a building, you need:
A) Floor area, ceiling height, and fan horsepower. B) A psychrometric chart and an enthalpy chart. C) The floor area, ceiling height, and an enthalpy chart. D) The floor area and ceiling height.
How do the staples that hold duct insulation together work?
What will be an ideal response?