Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Consider the following timeline using two processors.

A. This timeline is an illegal schedule.
B. This is the timeline one gets using the critical-path algorithm.
C. This timeline is an optimal schedule.
D. This is the timeline one gets using the decreasing-time algorithm.
E. none of these


Answer: E

Mathematics

You might also like to view...

Provide an appropriate response.Let sk denote the kth partial sum of the alternating harmonic series. If e(10) denotes the absolute value of the error in approximating ln 2 by , compute floor , where floor(x) denotes the integer floor (or greatest integer) function.

A. 20 B. 22 C. 19 D. 21

Mathematics

Find the perimeter of the figure.Square

A. 15 mi B. 112.5 mi C. 30 mi D. 40 mi

Mathematics

Estimate an answer to the problem.An advertisement states that television sets are on sale at B&G Electronics. The sale prices are:  set, $147.99;  set, $201.95;  set, $231.99; 27-inch set, $299.97;  set, $502.97. Estimate the approximate number of 

style="vertical-align: -4.0px;" /> sets that can be bought for $2729. A. 12 B. 19 C. 9 D. 5

Mathematics

Find a general term for the geometric sequence.625, 125, . . .

A. an = 625 n - 1
B. an = 625(5) n - 1
C. an = 625 n - 1
D. an = 625 n - 1

Mathematics