What is the objective of critical path analysis?
What will be an ideal response?
Critical path analysis determines the longest path through a network of activities. This longest path is the key to making the schedule that provides for completing all activities in the shortest time. Critical path analysis identifies those activities critical to timely completion of all activities so they can receive management focus.
You might also like to view...
The ________ includes keeping records of all property and money received and expended during the course of an agency
A) duty of accountability B) duty of termination C) duty to reimburse D) duty to notify
A minimization objective function could be used by the modeler in any of the following situations except:
a. When trying to optimize profit. b. When trying to minimize production waste. c. When trying to improve processing times. d. When trying to optimize cost.
A trust is a legal entity that can only exist for a year.
Answer the following statement true (T) or false (F)
Patty is a poor college student struggling to work and keep up with her studies. Fred, her uncle, promises to pay Patty support of $200 per month for the next six months. Although Fred didn't ask her to, she quits her current job in order to devote full time to her studies for the next six months. Fred makes one payment and then stops with no explanation. If Patty sues, what is the likely result?
A)Fred would win, as he did not ask Patty to quit her job. B)Patty would win, as a contract was formed when Fred promised to pay her the support. C)Fred would win, as family members cannot sue each other for breach of an oral promise. D)Patty may win under the doctrine of promissory estoppel.