Development of a(n) _____ leads to creation of a schedule and budget.

a. work breakdown structure
b. organization breakdown structure
c. Web planner
d. Gantt chart


a. work breakdown structure
Development of a work breakdown structure leads to creation of a schedule and budget. A work breakdown structure is an outline of thework to be done to complete the project.

Computer Science & Information Technology

You might also like to view...

The echo builtin copies its arguments to the screen. Given the following command line and its output, how can you repeat the command line with- out retyping it (Sobell, page 31)?

$ echo hi there hi there After giving the preceding command, how can you edit the command to replace hi with hello (Sobell, page 31)?

Computer Science & Information Technology

A leader is a series of characters that fill in the gap between two tabbed items

Indicate whether the statement is true or false

Computer Science & Information Technology

Create a SlideShow class that holds a list of slides and shows each slide one at a time.

What will be an ideal response?

Computer Science & Information Technology

With the vertical-align property, the center value vertically centers an image with the text.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology