A project’s variance is ______.

a. the sum of the variances of all of its critical activities
b. the average of the variances of all of its critical activities
c. the maximum of the variances of all of its critical activities
d. the minimum of the variances of all of its critical activities


a. the sum of the variances of all of its critical activities

Business

You might also like to view...

A conditional promise to pay is not a negotiable instrument.

Answer the following statement true (T) or false (F)

Business

Since 1947 and the end of the World War II era, the goal of the General Agreement on Tariffs and Trade (GATT) has been to restrict world trade

Indicate whether the statement is true or false

Business

In 2006, Intel introduced a low-cost laptop called the______

Fill in the blank(s) with correct word

Business

Many indicators of the macroeconomic environment such as GNP, interest rates, savings rates, trade and budget deficits/surplus, and so forth, are interrelated. Explain.

What will be an ideal response?

Business