The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.
Answer the following statement true (T) or false (F)
False
The time estimates for the work packages and network times were made independently with the implicit assumption that resources would be available. This may or may not be the case.
You might also like to view...
A global company that uses market skimming as a pricing strategy is likely to invite charges of "dumping" by competitors in host-country markets
Indicate whether the statement is true or false
All Things Digital Company starts the year with a credit balance of $3500 in its Estimated Warranty Payable account. During the year, there were $224,000 in sales and $4800 in warranty repair payments. All Things Digital estimates warranty expense at 2% of sales. At the end of the year, what is the balance in the Estimated Warranty Payable account?
A) $4480 debit B) $4800 credit C) $3500 debit D) $3180 credit
Brian recommends that the organization focus on selling its products to people aged 65 and older. Brian is recommending the ________ strategy.
A. senior B. cost leadership C. differentiation D. niche E. None of the above
An employee can claim workers compensation even if the injury occurred during a lunch break, off work premises as long as it occurred during the employees typical work hours
Indicate whether the statement is true or false